gptkbp:instance_of
|
gptkb:wind
|
gptkbp:benefits
|
local investment
|
gptkbp:capacity
|
659 MW
|
gptkbp:construction_started
|
gptkb:2017
gptkb:2018
|
gptkbp:country
|
gptkb:United_Kingdom
|
gptkbp:developer
|
gptkb:DONG_Energy
|
gptkbp:development_cost
|
£1.5 billion
|
gptkbp:electrification
|
gptkb:Orsted
|
gptkbp:environmental_impact
|
completed
reduces carbon emissions
|
gptkbp:funding
|
private investment
|
gptkbp:grid_position
|
gptkb:Walney_Island_substation
gptkb:National_Grid
|
gptkbp:has_ability
|
659 MW
|
gptkbp:has_beach
|
19 km
|
https://www.w3.org/2000/01/rdf-schema#label
|
Walney Extension Wind Farm
|
gptkbp:impact
|
economic growth in region
|
gptkbp:location
|
gptkb:Irish_Sea
|
gptkbp:maintenance
|
gptkb:Barrow-in-Furness
|
gptkbp:operational_since
|
gptkb:2018
|
gptkbp:owner
|
gptkb:Orsted
|
gptkbp:part_of
|
gptkb:Walney_Wind_Farm_cluster
|
gptkbp:power_source
|
renewable energy
clean energy generation
sufficient for 600,000 homes
UK's renewable energy supply
2.5 TWh annually
around 2.5 TWh
|
gptkbp:production_status
|
operational
|
gptkbp:project
|
gptkb:2018
|
gptkbp:scope
|
large scale wind energy project
|
gptkbp:sustainability_efforts
|
renewable energy targets
|
gptkbp:turbine_efficiency
|
high efficiency turbines
|
gptkbp:turbine_output
|
8 MW per turbine
|
gptkbp:turbine_type
|
gptkb:Siemens_Gamesa_SG_8.0-167
gptkb:Siemens_Gamesa
87
200 m
8 MW
advanced wind turbine technology
659 MW
commercial wind farm
87 turbines
|
gptkbp:water_resistance
|
high wind speeds
|
gptkbp:wind_farm_area
|
145 km²
|
gptkbp:wind_farm_developer
|
gptkb:Orsted
|
gptkbp:wind_farm_investment
|
significant investment in renewables
|
gptkbp:wind_farm_location
|
offshore
|
gptkbp:wind_farm_management
|
managed by Orsted
|
gptkbp:wind_farm_significance
|
largest operational offshore wind farm in the world at the time of completion.
|
gptkbp:year
|
gptkb:2018
|
gptkbp:year_created
|
September 2018
|
gptkbp:bfsParent
|
gptkb:Siemens_Gamesa_Renewable_Energy
|
gptkbp:bfsLayer
|
5
|