Statements (21)
Predicate | Object |
---|---|
gptkbp:instanceOf |
electricity transmission line
|
gptkbp:alsoKnownAs |
SüdLink
|
gptkbp:country |
gptkb:Germany
|
gptkbp:endPoint |
gptkb:Bergrheinfeld
|
https://www.w3.org/2000/01/rdf-schema#label |
SuedLink
|
gptkbp:length |
700 km
|
gptkbp:operatingSystem |
525 kV
|
gptkbp:operator |
gptkb:TenneT
gptkb:TransnetBW |
gptkbp:part_of |
German energy transition
|
gptkbp:planned_commissioning |
2028
|
gptkbp:projectCost |
approx. €10 billion
|
gptkbp:purpose |
transmit wind power from north to south Germany
|
gptkbp:regulates |
gptkb:Bundesnetzagentur
|
gptkbp:route |
Wilster to Bergrheinfeld
|
gptkbp:startPoint |
gptkb:Wilster
|
gptkbp:status |
under construction
|
gptkbp:technology |
underground cable
|
gptkbp:type |
gptkb:HVDC
|
gptkbp:bfsParent |
gptkb:German_power_grid
|
gptkbp:bfsLayer |
7
|