Statements (21)
| Predicate | Object |
|---|---|
| gptkbp:instanceOf |
gptkb:electricity_transmission_line
|
| gptkbp:alsoKnownAs |
SüdLink
|
| gptkbp:country |
gptkb:Germany
|
| gptkbp:endPoint |
gptkb:Bergrheinfeld
|
| gptkbp:length |
700 km
|
| gptkbp:operatingSystem |
525 kV
|
| gptkbp:operator |
gptkb:TenneT
gptkb:TransnetBW |
| gptkbp:part_of |
German energy transition
|
| gptkbp:planned_commissioning |
2028
|
| gptkbp:projectCost |
approx. €10 billion
|
| gptkbp:purpose |
transmit wind power from north to south Germany
|
| gptkbp:regulates |
gptkb:Bundesnetzagentur
|
| gptkbp:route |
Wilster to Bergrheinfeld
|
| gptkbp:startPoint |
gptkb:Wilster
|
| gptkbp:status |
under construction
|
| gptkbp:technology |
underground cable
|
| gptkbp:type |
gptkb:HVDC
|
| gptkbp:bfsParent |
gptkb:German_power_grid
|
| gptkbp:bfsLayer |
8
|
| https://www.w3.org/2000/01/rdf-schema#label |
SuedLink
|