Statements (25)
| Predicate | Object |
|---|---|
| gptkbp:instanceOf |
gptkb:railway_line
|
| gptkbp:builtBy |
gptkb:China_Road_and_Bridge_Corporation
|
| gptkbp:connects |
gptkb:Mombasa
Nairobi |
| gptkbp:electrification |
not electrified
|
| gptkbp:extensionPlannedTo |
gptkb:Malaba
gptkb:Naivasha Kisumu |
| gptkbp:fundedBy |
gptkb:Chinese_government
|
| gptkbp:gauge |
1435 mm
|
| gptkbp:length |
approximately 472 km
|
| gptkbp:locatedIn |
gptkb:Kenya
|
| gptkbp:maximumSpeed |
120 km/h (passenger)
80 km/h (freight) |
| gptkbp:opened |
2017
|
| gptkbp:operator |
gptkb:Kenya_Railways_Corporation
|
| gptkbp:partOf |
gptkb:Northern_Corridor_Integration_Project
|
| gptkbp:projectCost |
approximately $3.6 billion
|
| gptkbp:purpose |
passenger transport
freight transport |
| gptkbp:replacedBy |
gptkb:Uganda_Railway_(meter_gauge)
|
| gptkbp:roadType |
single track
|
| gptkbp:bfsParent |
gptkb:LAPSSET_Corridor_Project
|
| gptkbp:bfsLayer |
6
|
| https://www.w3.org/2000/01/rdf-schema#label |
Standard Gauge Railway
|