Plant Vogtle Units 3 and 4 (nuclear expansion)
URI:
https://gptkb.org/entity/Plant_Vogtle_Units_3_and_4_(nuclear_expansion)
GPTKB entity
Statements (33)
Predicate
Object
gptkbp:instanceOf
nuclear power plant expansion project
gptkbp:actualCompletion
2023 (Unit 3), 2024 (Unit 4)
gptkbp:capacity
1,117 MW
2,234 MW
gptkbp:constructionContractor
gptkb:Bechtel
gptkbp:constructionStartYear
March 2013
gptkbp:cost
over $30 billion
gptkbp:country
gptkb:United_States
gptkbp:delays
multiple years
gptkbp:fuelType
gptkb:uranium
gptkbp:gridConnectionDateUnit3
April 2023
gptkbp:gridConnectionDateUnit4
March 2024
https://www.w3.org/2000/01/rdf-schema#label
Plant Vogtle Units 3 and 4 (nuclear expansion)
gptkbp:initialPlannedCompletion
2016
gptkbp:location
gptkb:Waynesboro,_Georgia,_United_States
gptkbp:notableFor
largest generator of clean energy in the US Southeast
first new nuclear reactors built in the US in the 21st century
gptkbp:owner
gptkb:Municipal_Electric_Authority_of_Georgia
gptkb:Dalton_Utilities
gptkb:Oglethorpe_Power
gptkb:Georgia_Power
gptkbp:parentCompany
gptkb:Southern_Company
gptkbp:partOf
gptkb:Plant_Vogtle
gptkbp:reactorSupplier
gptkb:Westinghouse_Electric_Company
gptkbp:reactorType
gptkb:AP1000
gptkbp:regulates
gptkb:U.S._Nuclear_Regulatory_Commission
gptkbp:significance
first AP1000 reactors in the US
largest nuclear construction project in US history
gptkbp:status
operational
gptkbp:unit3CommercialOperationDate
July 31, 2023
gptkbp:unit4CommercialOperationDate
April 29, 2024
gptkbp:bfsParent
gptkb:Georgia_Power_Company
gptkbp:bfsLayer
7