Statements (24)
Predicate | Object |
---|---|
gptkbp:instanceOf |
metro rail project phase
|
gptkbp:country |
gptkb:India
|
gptkbp:electrification |
750 V DC third rail
|
gptkbp:endPoint |
gptkb:Chandpole
|
gptkbp:extendsTo |
Phase 1B
|
https://www.w3.org/2000/01/rdf-schema#label |
Jaipur Metro Phase 1
|
gptkbp:length |
9.63 km
|
gptkbp:location |
Jaipur
|
gptkbp:numberOfStations |
9
|
gptkbp:opened |
3 June 2015
|
gptkbp:operator |
gptkb:Jaipur_Metro_Rail_Corporation
|
gptkbp:partOf |
gptkb:Jaipur_Metro
|
gptkbp:period |
Phase 1A
|
gptkbp:phase1BEndStation |
gptkb:Badi_Chaupar
|
gptkbp:phase1BLength |
2.349 km
|
gptkbp:phase1BNumberOfStations |
2
|
gptkbp:phase1BOpeningDate |
23 September 2020
|
gptkbp:phase1BStartStation |
gptkb:Chandpole
|
gptkbp:railwayLine |
gptkb:Pink_Line
|
gptkbp:startPoint |
gptkb:Mansarovar
|
gptkbp:status |
operational
|
gptkbp:trackGauge |
standard gauge
|
gptkbp:bfsParent |
gptkb:Jaipur_Metro_Rail_Corporation_Limited
|
gptkbp:bfsLayer |
7
|