Statements (28)
| Predicate | Object |
|---|---|
| gptkbp:instanceOf |
gptkb:infrastructure_project_phase
|
| gptkbp:budget |
over £1 billion
|
| gptkbp:includes |
demolition
site clearance archaeological investigations environmental mitigation utility diversions |
| gptkbp:location |
gptkb:Buckinghamshire
gptkb:London gptkb:Warwickshire gptkb:West_Midlands gptkb:Northamptonshire gptkb:Staffordshire |
| gptkbp:mainContractor |
gptkb:Murphy
gptkb:Costain_Skanska_joint_venture Laing O’Rourke |
| gptkbp:notableAction |
St James’s Gardens exhumation
demolition of Euston properties removal of utilities at Old Oak Common |
| gptkbp:notableClient |
gptkb:HS2_Ltd
|
| gptkbp:partOf |
gptkb:High_Speed_2
|
| gptkbp:purpose |
prepare sites for main HS2 construction
|
| gptkbp:startDate |
2017
|
| gptkbp:status |
ongoing (as of 2023)
|
| gptkbp:bfsParent |
gptkb:Fusion_(Morgan_Sindall,_BAM_Nuttall,_Ferrovial)
gptkb:LM_(Laing_O'Rourke,_Murphy) |
| gptkbp:bfsLayer |
7
|
| https://www.w3.org/2000/01/rdf-schema#label |
HS2 enabling works
|