Statements (16)
| Predicate | Object |
|---|---|
| gptkbp:instanceOf |
gptkb:HVDC_transmission_line
|
| gptkbp:capacity |
1800 MW
|
| gptkbp:commissioned |
1978
|
| gptkbp:country |
gptkb:Canada
|
| gptkbp:endPoint |
gptkb:Dorsey_Converter_Station
|
| gptkbp:length |
937 km
|
| gptkbp:locatedIn |
gptkb:Manitoba
|
| gptkbp:operatedBy |
gptkb:Manitoba_Hydro
|
| gptkbp:operatingSystem |
±500 kV
|
| gptkbp:partOf |
Nelson River HVDC system
|
| gptkbp:purpose |
transmit hydroelectric power from northern Manitoba to southern Manitoba
|
| gptkbp:startPoint |
Radisson Converter Station
|
| gptkbp:type |
overhead transmission line
|
| gptkbp:bfsParent |
gptkb:Bipole_III_transmission_line
|
| gptkbp:bfsLayer |
7
|
| https://www.w3.org/2000/01/rdf-schema#label |
Bipole II transmission line
|