gptkbp:instanceOf
|
offshore wind farm project
|
gptkbp:approvedBy
|
gptkb:U.S._Department_of_the_Interior
|
gptkbp:capacity
|
800 MW
|
gptkbp:constructionStartYear
|
2021
|
gptkbp:developer
|
gptkb:Avangrid_Renewables
gptkb:Copenhagen_Infrastructure_Partners
|
gptkbp:distanceFromMainland
|
15 miles
|
gptkbp:expectedCO2Reduction
|
1.68 million metric tons per year
|
gptkbp:expectedOperationDate
|
2024
|
gptkbp:expectedToPower
|
400,000 homes
|
gptkbp:firstLargeScaleOffshoreWindFarmIn
|
gptkb:United_States
|
gptkbp:gridConnection
|
gptkb:Barnstable,_Massachusetts
|
gptkbp:hasTower
|
62
|
https://www.w3.org/2000/01/rdf-schema#label
|
Vineyard Wind
|
gptkbp:leaseDuration
|
OCS-A 0501
|
gptkbp:locatedOffCoastOf
|
gptkb:Martha's_Vineyard
|
gptkbp:location
|
gptkb:Massachusetts,_United_States
|
gptkbp:offtakeAgreement
|
gptkb:National_Grid
Eversource
Unitil
|
gptkbp:powerPurchaseAgreementWith
|
Massachusetts utilities
|
gptkbp:projectCost
|
$2.8 billion
|
gptkbp:turbine_manufacturer
|
gptkb:GE_Renewable_Energy
|
gptkbp:turbineType
|
GE Haliade-X
|
gptkbp:website
|
https://www.vineyardwind.com/
|
gptkbp:bfsParent
|
gptkb:Haliade-X_offshore_wind_turbine
gptkb:Haliade-X
gptkb:CIP_(Copenhagen_Infrastructure_Partners)
|
gptkbp:bfsLayer
|
7
|