Third Runway System

GPTKB entity

Statements (23)
Predicate Object
gptkbp:instanceOf airport infrastructure project
gptkbp:completedIn 2024
gptkbp:constructionStartYear 2016
gptkbp:country gptkb:Hong_Kong
gptkbp:environmentalImpact approved in 2014
gptkbp:estimatedCost HK$141.5 billion
https://www.w3.org/2000/01/rdf-schema#label Third Runway System
gptkbp:includes baggage handling system
third runway
expanded Terminal 2
new automated people mover system
new passenger concourse
gptkbp:locatedIn gptkb:Hong_Kong_International_Airport
gptkbp:mainContractor gptkb:China_State_Construction_Engineering_(Hong_Kong)_Limited
gptkbp:operator gptkb:Airport_Authority_Hong_Kong
gptkbp:publicConsultation conducted in 2011
gptkbp:purpose increase airport capacity
gptkbp:relatedTo Hong Kong International Airport expansion
gptkbp:runwayLength 60 meters
3,800 meters
gptkbp:status under construction
gptkbp:bfsParent gptkb:Chek_Lap_Kok_Airport
gptkbp:bfsLayer 6