Program Evaluation Review Technique
GPTKB entity
Statements (29)
Predicate | Object |
---|---|
gptkbp:instanceOf |
project management methodology
|
gptkbp:abbreviation |
gptkb:PERT
|
gptkbp:application |
project planning
project scheduling project control |
gptkbp:calculationMethod |
expected time = (optimistic + 4*most likely + pessimistic)/6
|
gptkbp:category |
operations research
project management |
gptkbp:developedBy |
gptkb:United_States_Navy
gptkb:Polaris_missile_project |
gptkbp:focusesOn |
time required to complete project tasks
|
https://www.w3.org/2000/01/rdf-schema#label |
Program Evaluation Review Technique
|
gptkbp:influenced |
modern project management techniques
|
gptkbp:introducedIn |
1950s
|
gptkbp:purpose |
analyze and represent tasks involved in completing a project
|
gptkbp:relatedTo |
Critical Path Method
|
gptkbp:step |
construct network diagram
determine task sequence estimate time for each activity identify critical path identify specific project tasks |
gptkbp:timeEstimateType |
most likely time
optimistic time pessimistic time |
gptkbp:uses |
network diagram
probabilistic time estimates |
gptkbp:visualizes |
gptkb:PERT_chart
|
gptkbp:bfsParent |
gptkb:PERT_chart
|
gptkbp:bfsLayer |
7
|