PERT (Program Evaluation and Review Technique)

GPTKB entity

Statements (23)
Predicate Object
gptkbp:instanceOf project management methodology
gptkbp:abbreviation gptkb:Program_Evaluation_and_Review_Technique
gptkbp:appliesTo large-scale projects
research and development projects
gptkbp:category project management tool
gptkbp:computes expected time
gptkbp:developedBy gptkb:U.S._Navy
gptkb:Polaris_missile_project
gptkbp:estimatedCost most likely time
optimistic time
pessimistic time
gptkbp:focusesOn uncertainty in project duration
https://www.w3.org/2000/01/rdf-schema#label PERT (Program Evaluation and Review Technique)
gptkbp:introducedIn 1950s
gptkbp:relatedTo Critical Path Method
gptkbp:usedFor project planning
project scheduling
project control
gptkbp:uses network diagram
probabilistic time estimates
gptkbp:visualizes gptkb:PERT_chart
gptkbp:bfsParent gptkb:Donald_G._Malcolm
gptkbp:bfsLayer 8