Statements (14)
| Predicate | Object |
|---|---|
| gptkbp:instanceOf |
gptkb:geothermal_power_project
|
| gptkbp:commissioned |
2021
|
| gptkbp:fundedBy |
gptkb:Top_Energy
|
| gptkbp:increasedCapacityBy |
32 MW
|
| gptkbp:location |
Ngawha, Northland, New Zealand
|
| gptkbp:operatedBy |
gptkb:Top_Energy
|
| gptkbp:powerSource |
geothermal
|
| gptkbp:purpose |
electricity generation
|
| gptkbp:regionServed |
gptkb:Far_North_District
|
| gptkbp:relatedTo |
gptkb:Ngawha_Geothermal_Power_Station
|
| gptkbp:totalCapacityAfterExpansion |
56 MW
|
| gptkbp:bfsParent |
gptkb:Ngawha_geothermal_field
|
| gptkbp:bfsLayer |
8
|
| https://www.w3.org/2000/01/rdf-schema#label |
Ngawha Expansion Project
|