Statements (20)
| Predicate | Object |
|---|---|
| gptkbp:instanceOf |
gptkb:wind
|
| gptkbp:capacity |
306 MW
|
| gptkbp:commissioned |
2009
|
| gptkbp:country |
gptkb:United_States
|
| gptkbp:gridConnection |
Intermountain Power Project transmission system
|
| gptkbp:hasTower |
97
|
| gptkbp:location |
gptkb:Millard_County,_Utah
gptkb:Beaver_County,_Utah |
| gptkbp:operator |
gptkb:First_Wind
|
| gptkbp:period |
gptkb:Phase_I
Phase II |
| gptkbp:phase_I_capacity |
203.5 MW
|
| gptkbp:phase_II_capacity |
102.5 MW
|
| gptkbp:purpose |
electricity generation
|
| gptkbp:status |
operational
|
| gptkbp:turbine_manufacturer |
Clipper Windpower
|
| gptkbp:turbineType |
Liberty 2.5 MW
|
| gptkbp:bfsParent |
gptkb:First_Wind
|
| gptkbp:bfsLayer |
7
|
| https://www.w3.org/2000/01/rdf-schema#label |
Milford Wind Corridor
|