gptkbp:instanceOf |
coal-fired power plant
|
gptkbp:capacity |
350 MW
|
gptkbp:commissioned |
1987
|
gptkbp:country |
gptkb:Serbia
|
gptkbp:emission_control |
flue-gas desulfurization system
|
gptkbp:expansion |
Kostolac B3 unit
|
gptkbp:expansion_project_capacity |
350 MW
|
gptkbp:expansion_project_status |
under construction (as of 2023)
|
gptkbp:fuel_source |
Drmno coal mine
|
gptkbp:fuelType |
gptkb:coal
|
gptkbp:gridConnection |
Serbian national grid
|
gptkbp:hasChimneyHeight |
281 meters
|
https://www.w3.org/2000/01/rdf-schema#label |
Kostolac B Power Plant
|
gptkbp:location |
gptkb:Kostolac,_Serbia
|
gptkbp:numberOfRooms |
2
|
gptkbp:operator |
gptkb:Elektroprivreda_Srbije
|
gptkbp:owner |
gptkb:Elektroprivreda_Srbije
|
gptkbp:status |
operational
|
gptkbp:total_electrical_capacity |
700 MW
|
gptkbp:website |
https://www.eps.rs/
|
gptkbp:bfsParent |
gptkb:Thermal_power_plants_in_Serbia
|
gptkbp:bfsLayer |
8
|