Predicate | Object |
---|---|
gptkbp:instanceOf |
gptkb:infrastructure
|
gptkbp:archaeologicalSite |
gptkb:London_King's_Cross_railway_station
|
gptkbp:architect |
gptkb:John_McAslan_+_Partners
|
gptkbp:awarded |
gptkb:Europa_Nostra_Award
|
gptkbp:cost |
£550 million
|
gptkbp:endDate |
2012
|
https://www.w3.org/2000/01/rdf-schema#label |
King's Cross remodelling
|
gptkbp:includes |
improved accessibility
new concourse demolition of 1972 extension restoration of original station façade track layout changes |
gptkbp:location |
gptkb:London
|
gptkbp:operator |
gptkb:Network_Rail
|
gptkbp:purpose |
improved passenger facilities
station redevelopment capacity increase |
gptkbp:relatedTo |
gptkb:King's_Cross_Central_redevelopment
gptkb:St_Pancras_railway_station |
gptkbp:startDate |
2005
|
gptkbp:bfsParent |
gptkb:East_Coast_Main_Line_upgrade
|
gptkbp:bfsLayer |