Statements (22)
| Predicate | Object |
|---|---|
| gptkbp:instanceOf |
gptkb:infrastructure
|
| gptkbp:archaeologicalSite |
gptkb:London_King's_Cross_railway_station
|
| gptkbp:architect |
gptkb:John_McAslan_+_Partners
|
| gptkbp:awarded |
gptkb:Europa_Nostra_Award
|
| gptkbp:cost |
£550 million
|
| gptkbp:endDate |
2012
|
| gptkbp:includes |
improved accessibility
new concourse demolition of 1972 extension restoration of original station façade track layout changes |
| gptkbp:location |
gptkb:London
|
| gptkbp:operator |
gptkb:Network_Rail
|
| gptkbp:purpose |
improved passenger facilities
station redevelopment capacity increase |
| gptkbp:relatedTo |
gptkb:King's_Cross_Central_redevelopment
gptkb:St_Pancras_railway_station |
| gptkbp:startDate |
2005
|
| gptkbp:bfsParent |
gptkb:East_Coast_Main_Line_upgrade
|
| gptkbp:bfsLayer |
7
|
| https://www.w3.org/2000/01/rdf-schema#label |
King's Cross remodelling
|