Statements (22)
Predicate | Object |
---|---|
gptkbp:instanceOf |
high-voltage direct current transmission line
|
gptkbp:capacity |
560 MW
|
gptkbp:commissioned |
1982
|
gptkbp:converterStationLocation |
gptkb:Inga
gptkb:Kolwezi |
gptkbp:country |
gptkb:Democratic_Republic_of_the_Congo
|
gptkbp:endPoint |
Shaba (now Katanga) region
|
https://www.w3.org/2000/01/rdf-schema#label |
Inga–Shaba HVDC
|
gptkbp:length |
1700 km
|
gptkbp:mainContractor |
gptkb:ABB
gptkb:Siemens |
gptkbp:notableFor |
first HVDC project in Africa
one of the longest HVDC lines in the world |
gptkbp:numberOfConverterStations |
2
|
gptkbp:operatingSystem |
±500 kV
|
gptkbp:owner |
gptkb:Société_Nationale_d'Électricité_(SNEL)
|
gptkbp:purpose |
transmit hydroelectric power from Inga Dam to mining region
|
gptkbp:regionServed |
gptkb:Katanga
gptkb:Kinshasa |
gptkbp:startPoint |
gptkb:Inga_Dam
|
gptkbp:bfsParent |
gptkb:HVDC
|
gptkbp:bfsLayer |
7
|