Statements (22)
Predicate | Object |
---|---|
gptkbp:instanceOf |
offshore wind farm
|
gptkbp:capacity |
1.4 GW
|
gptkbp:commissioned |
2022
|
gptkbp:constructionStarted |
2018
|
gptkbp:electrification |
2021
|
gptkbp:engineType |
gptkb:GE_Haliade-X
|
gptkbp:environmentalImpact |
completed
|
gptkbp:gridConnection |
National Grid
|
gptkbp:hasFieldOfUse |
fixed-bottom
|
https://www.w3.org/2000/01/rdf-schema#label |
Hornsea Two
|
gptkbp:investmentFocus |
£6 billion
|
gptkbp:length |
89 km
|
gptkbp:locatedIn |
gptkb:North_Sea
|
gptkbp:maintenance |
gptkb:Grimsby
|
gptkbp:numberOfTeams |
165
|
gptkbp:operatedBy |
Orsted
|
gptkbp:powerOutput |
enough to power 1.3 million homes
|
gptkbp:project |
operational
Orsted East_Riding_of_Yorkshire,_England |
gptkbp:supplyChain |
local and international
|
gptkbp:sustainability |
wind
|