Statements (22)
Predicate | Object |
---|---|
gptkbp:instanceOf |
wind
|
gptkbp:capacity |
2.4 GW
|
gptkbp:country |
gptkb:United_Kingdom
|
gptkbp:developer |
gptkb:Ørsted
|
gptkbp:distanceFromMainland |
121 km
|
gptkbp:expectedCommissioning |
mid-2020s
|
gptkbp:exportCableLandfall |
gptkb:Norfolk,_England
|
gptkbp:gridConnection |
gptkb:Norwich_Main_substation
|
gptkbp:hasTower |
up to 231
|
https://www.w3.org/2000/01/rdf-schema#label |
Hornsea Project Three
|
gptkbp:location |
gptkb:North_Sea
|
gptkbp:notableProject |
gptkb:Hornsea_Project_Two
gptkb:Hornsea_Project_One |
gptkbp:offtakeAgreement |
gptkb:CfD_(Contract_for_Difference)
|
gptkbp:owner |
gptkb:Ørsted
|
gptkbp:partOf |
gptkb:Hornsea_Wind_Farm_Zone
|
gptkbp:planningConsentGranted |
December 2020
|
gptkbp:status |
under development
|
gptkbp:turbine_manufacturer |
gptkb:Siemens_Gamesa
|
gptkbp:website |
https://hornseaproject3.co.uk/
|
gptkbp:bfsParent |
gptkb:Hornsea_Wind_Farm_Zone
|
gptkbp:bfsLayer |
7
|