Hai Duong Thermal Power Plant
GPTKB entity
Statements (18)
| Predicate | Object |
|---|---|
| gptkbp:instanceOf |
gptkb:hydroelectric_power_station
|
| gptkbp:capacity |
600 MW
1,200 MW |
| gptkbp:commissioned |
2021
|
| gptkbp:constructionStartYear |
2016
|
| gptkbp:country |
gptkb:Vietnam
|
| gptkbp:fuelType |
gptkb:coal
|
| gptkbp:location |
gptkb:Hai_Duong_Province
|
| gptkbp:mainContractor |
Chengda Engineering Company
Southwest Electric Power Design Institute |
| gptkbp:notableProject |
build-operate-transfer (BOT)
|
| gptkbp:numberOfRooms |
2
|
| gptkbp:operator |
Jaks Hai Duong Power Company Limited
|
| gptkbp:owner |
Jaks Resources Berhad
|
| gptkbp:status |
operational
|
| gptkbp:bfsParent |
gptkb:Taekwang_Power
|
| gptkbp:bfsLayer |
7
|
| https://www.w3.org/2000/01/rdf-schema#label |
Hai Duong Thermal Power Plant
|