Statements (21)
Predicate | Object |
---|---|
gptkbp:instanceOf |
gptkb:hydroelectric_power_station
|
gptkbp:builtBy |
gptkb:Electricity_Supply_Board
|
gptkbp:capacity |
65 MW
|
gptkbp:catchmentArea |
River Erne basin
|
gptkbp:commissioned |
1950
|
gptkbp:country |
gptkb:Ireland
gptkb:United_Kingdom |
gptkbp:dam |
Assaroe Dam
|
https://www.w3.org/2000/01/rdf-schema#label |
Erne Hydroelectric Scheme
|
gptkbp:location |
gptkb:County_Donegal
gptkb:County_Fermanagh |
gptkbp:numberOfStations |
2
|
gptkbp:operator |
gptkb:Electricity_Supply_Board
|
gptkbp:powerSource |
Cathaleen's Fall Power Station
Clady Power Station |
gptkbp:purpose |
electricity generation
|
gptkbp:regionServed |
gptkb:Northwest_Ireland
|
gptkbp:river |
gptkb:River_Erne
|
gptkbp:status |
operational
|
gptkbp:bfsParent |
gptkb:Cathaleen's_Fall_hydroelectric_power_station
|
gptkbp:bfsLayer |
8
|