gptkbp:instanceOf
|
gptkb:hydroelectric_power_station
|
gptkbp:annualGeneration
|
1,650 GWh
|
gptkbp:capacity
|
1,728 MW
|
gptkbp:commissioned
|
1984
|
gptkbp:constructionCost
|
£425 million
|
gptkbp:constructionStartYear
|
1974
|
gptkbp:country
|
gptkb:United_Kingdom
|
gptkbp:designedBy
|
gptkb:Sir_William_Halcrow_&_Partners
|
gptkbp:elevation
|
536 metres
|
gptkbp:emergencyStartTime
|
12 seconds
|
gptkbp:fuelType
|
gptkb:water
|
gptkbp:gridConnection
|
gptkb:National_Grid_(UK)
|
gptkbp:gridFrequencyResponse
|
yes
|
gptkbp:hasTower
|
6
|
gptkbp:hasVisitorCenter
|
gptkb:Electric_Mountain_Visitor_Centre
|
https://www.w3.org/2000/01/rdf-schema#label
|
Dinorwig Power Station
|
gptkbp:location
|
gptkb:Llanberis,_Gwynedd,_Wales
|
gptkbp:mainContractor
|
gptkb:Alfred_McAlpine
|
gptkbp:maximumSpeed
|
1,728 MW
|
gptkbp:nickname
|
gptkb:Electric_Mountain
|
gptkbp:notableFor
|
one of the largest pumped-storage power stations in Europe
|
gptkbp:operatedBy
|
gptkb:First_Hydro_Company
|
gptkbp:ownedBy
|
gptkb:Engie
|
gptkbp:purpose
|
electricity grid balancing
peak load supply
|
gptkbp:reservoirName
|
gptkb:Llyn_Peris
gptkb:Marchlyn_Mawr
|
gptkbp:status
|
operational
|
gptkbp:tunnel
|
10 miles
|
gptkbp:undergroundCaverns
|
yes
|
gptkbp:website
|
https://www.electricmountain.co.uk/
|
gptkbp:bfsParent
|
gptkb:Llanberis
gptkb:Llyn_Padarn
|
gptkbp:bfsLayer
|
6
|