BorWin3 Offshore Grid Connection
GPTKB entity
Statements (23)
| Predicate | Object |
|---|---|
| gptkbp:instanceOf |
gptkb:offshore_grid_connection
|
| gptkbp:capacity |
900 MW
|
| gptkbp:commissioned |
2019
|
| gptkbp:converter_station |
gptkb:Emden/Ost
gptkb:BorWin_Gamma |
| gptkbp:country |
gptkb:Germany
|
| gptkbp:length |
160 km
|
| gptkbp:location |
gptkb:North_Sea
|
| gptkbp:operatingSystem |
320 kV
|
| gptkbp:operator |
gptkb:TenneT
|
| gptkbp:partner |
gptkb:Siemens
gptkb:Petrofac |
| gptkbp:purpose |
connect offshore wind farms to mainland grid
|
| gptkbp:region |
gptkb:Lower_Saxony
|
| gptkbp:technology |
gptkb:HVDC
|
| gptkbp:transmission |
gptkb:submarine_cable
underground cable |
| gptkbp:wind_farms_connected |
gptkb:Veja_Mate
gptkb:Nordsee_One gptkb:Deutsche_Bucht |
| gptkbp:bfsParent |
gptkb:Petrofac
|
| gptkbp:bfsLayer |
7
|
| https://www.w3.org/2000/01/rdf-schema#label |
BorWin3 Offshore Grid Connection
|