Statements (23)
| Predicate | Object | 
|---|---|
| gptkbp:instanceOf | gptkb:electricity_transmission_line | 
| gptkbp:approvalYear | 2010 | 
| gptkbp:approvedBy | gptkb:Parliament_of_the_United_Kingdom | 
| gptkbp:commissioned | 2015 | 
| gptkbp:constructionStartYear | 2010 | 
| gptkbp:controversy | environmental impact | 
| gptkbp:country | gptkb:United_Kingdom | 
| gptkbp:endPoint | gptkb:Denny | 
| gptkbp:hasTower | over 600 | 
| gptkbp:length | 220 km | 
| gptkbp:locatedIn | gptkb:Scotland | 
| gptkbp:operatingSystem | 400 kV | 
| gptkbp:operator | gptkb:SP_Energy_Networks Scottish and Southern Electricity Networks | 
| gptkbp:owner | gptkb:Scottish_Hydro_Electric_Transmission Scottish Power Transmission | 
| gptkbp:passesThrough | gptkb:Cairngorms_National_Park | 
| gptkbp:purpose | transmit electricity from renewable sources in the north to the south of Scotland | 
| gptkbp:replacedBy | 132 kV transmission line | 
| gptkbp:startPoint | gptkb:Beauly | 
| gptkbp:bfsParent | gptkb:Stronelairg_Wind_Farm | 
| gptkbp:bfsLayer | 8 | 
| https://www.w3.org/2000/01/rdf-schema#label | Beauly-Denny line |