gptkbp:instanceOf |
dam
|
gptkbp:affiliatedWith |
access roads
power transmission lines |
gptkbp:benefits |
water supply
irrigation flood control |
gptkbp:built |
2000
concrete gravity dam |
gptkbp:community_impact |
economic development
job creation displacement of local communities |
gptkbp:construction_cost |
approximately $100 million
|
gptkbp:engineType |
gptkb:Francis_turbine
|
gptkbp:environmental_impact |
habitat alteration
sedimentation issues |
gptkbp:height |
100 meters
|
https://www.w3.org/2000/01/rdf-schema#label |
Batang Hari Dam
|
gptkbp:is_a_source_of |
hydroelectric power generation
|
gptkbp:length |
1,200 meters
|
gptkbp:lighting |
200 million cubic meters
|
gptkbp:location |
Jambi, Indonesia
|
gptkbp:maintenance |
regular inspections
sediment management |
gptkbp:operational_status |
120 MW
|
gptkbp:operator |
gptkb:Perusahaan_Listrik_Negara_(PLN)
|
gptkbp:powerOutput |
annual energy generation of 500 GWh
|
gptkbp:project |
public-private partnership
|
gptkbp:region |
supports local economy
provides renewable energy |
gptkbp:regulatoryBody |
gptkb:Indonesian_Ministry_of_Environment_and_Forestry
gptkb:Indonesian_Ministry_of_Energy_and_Mineral_Resources |
gptkbp:research_focus |
environmental impact assessments
hydrology studies |
gptkbp:reservoir |
1,000 million cubic meters
|
gptkbp:river |
gptkb:Batang_Hari_River
|
gptkbp:safetyFeatures |
regular safety drills
emergency action plan |
gptkbp:spillwayType |
gated spillway
|
gptkbp:tourism |
recreational activities
scenic views |
gptkbp:type |
embankment dam
|
gptkbp:waterQuality |
ongoing
|
gptkbp:wildlife |
affected by dam construction
|