gptkbp:instance_of
|
gptkb:wind
|
gptkbp:armament
|
75 m
|
gptkbp:benefits
|
provides local jobs
|
gptkbp:capacity
|
210 MW
|
gptkbp:collaborations
|
collaborations with universities
|
gptkbp:community_engagement
|
local consultations conducted
|
gptkbp:construction_started
|
gptkb:2013
gptkb:2014
|
gptkbp:developer
|
gptkb:DONG_Energy
|
gptkbp:development_cost
|
1.3 billion GBP
|
gptkbp:disbandment_date
|
expected 2044
|
gptkbp:emissions_standard
|
zero emissions during operation
approximately 300,000 tons per year
|
gptkbp:environmental_concerns
|
supports UK energy policy goals
|
gptkbp:environmental_impact
|
completed
reduces reliance on fossil fuels
|
gptkbp:expansion_plans
|
potential for expansion exists
|
gptkbp:funding
|
partially funded by government grants
|
gptkbp:grid_position
|
gptkb:National_Grid
subsea cable
|
gptkbp:has_beach
|
8 km
|
https://www.w3.org/2000/01/rdf-schema#label
|
Westermost Rough Wind Farm
|
gptkbp:is_monitored_by
|
installed systems
real-time monitoring in place
|
gptkbp:location
|
gptkb:North_Sea
|
gptkbp:maintenance
|
gptkb:Grimsby
|
gptkbp:max_speed
|
average 8.5 m/s
|
gptkbp:occurs_annually
|
approximately 700 GWh
|
gptkbp:operational_since
|
gptkb:2014
|
gptkbp:owner
|
gptkb:DONG_Energy
|
gptkbp:part_of
|
Greater Gabbard Wind Farm cluster
|
gptkbp:power_source
|
renewable energy
enough to power 150,000 homes
|
gptkbp:production_status
|
operational
|
gptkbp:public_access
|
no public access to site
|
gptkbp:region
|
gptkb:East_Riding_of_Yorkshire
|
gptkbp:safety_record
|
excellent
|
gptkbp:storage
|
not applicable
|
gptkbp:supply_chain
|
local suppliers involved
|
gptkbp:turbine_type
|
gptkb:35
gptkb:Siemens_Gamesa_SG_6.0-154
gptkb:Siemens_Gamesa
up to 180 m
commercial wind farm
|
gptkbp:wind_farm_capacity_factor
|
approximately 45%
|
gptkbp:bfsParent
|
gptkb:DONG_Energy
|
gptkbp:bfsLayer
|